Notice of Works – Dinghy Clubhouse

Preparations are now underway to replace the roof of the Dinghy Clubhouse. The repairs are scheduled to begin from the 20th of August until the end of September 2021, during this period there will be limited access to the site. Please adhere to all signage placed around the Dinghy Clubhouse. The Sailing Office will be in contact with Members in regards to moving boats and equipment.

 

Section 1: Marks shed and gym (Starts Monday 30th August)
Preparations for works required:
– Move Pacers and Plastic Optimists from the West Side of the building out onto grassed Area 1
– Move 29ers and Mustos from East end into compound/Area 1

Section 2: Laser and Optimist stores (Planned to start Monday 6th September)
Preparations for works required:
– Move regular use Lasers and Optimists from inside to fenced Area 2

Section 3: Dinghy club room and office (Planned to start 13th September)
Note: Limited access to Dinghy clubhouse area and office during works